"Everyone is arguing about AI data centers, but have you ever seen how one actually gets built? This is ranch land outside Abilene, a small city in West Texas, in the spring of 2024. And this is the same land today. Eight buildings built to work together as one of the biggest computers on Earth...."
[00:00:00] Speaker 1: Everyone is arguing about AI data centers, but have you ever seen how one actually gets built? This is ranch land outside Abilene, a small city in West Texas, in the spring of 2024. And this is the same land today. Eight buildings built to work together as one of the biggest computers on Earth. They went up so fast that on the state's own paperwork, the job is called Project Ludacris. Inside, the builders say, the halls are so alike that if you walk 20 steps into one, you have seen all of it. A single cabinet of its chips weighs as much as a car and draws the electricity of a whole street of homes, and there are thousands of them. Together, they need more power than several cities the size of the one next door, which is how the descendants of a jet engine came to be standing in a Texas field. Today, we follow the whole build, from the first hole in the ground to the day the chips were switched on. You will see what is really inside one of these buildings, why it needs so much electricity, where its water goes, and what it all costs. Whatever you think of them, by the end you will know exactly what one is. Start with the ground, and with a fair question. Why here? Abilene is a city of about 130,000 people on the plains of West Texas. The land around it is open ranch country, but so is a great deal of Texas. What this patch had was the one thing that usually takes years to get, a heavy connection to the power grid. It was already standing in the field, built from 2022 for an earlier plan to mine Bitcoin here. Keep an eye on that power line, because this story keeps coming back to it. In March 2024, three months before anyone dug a hole, the architects, the engineers, and the contractors sat down in one room. A superintendent at the electrical contractor remembers what the owner told them. Ignore the way every other data center has been done. What they drew is simple, and that is the point. Each building is a single story in the shape of the letter H. Four identical halls hold the computers, the bar in the middle holds the machinery that keeps them running. One building covers four and a half hectares, more than six soccer fields under a single roof. And every hall is the same hall. The lead builder says that if you walk 20 steps in, you have seen the entire thing. Sameness is what makes speed possible. Every piece of steel sits on one repeating grid, so the pieces are interchangeable. The walls come in only four kinds of panels. And nothing waited for anything else. The steel was ordered within 30 days, and the biggest machines were bought before the drawings were finished. Designing a steel frame of this size normally takes six to eight months. Here, the engineers say, it took five weeks. Someone has to pay for all of this long before a chip earns anything, and the arrangement is a chain of three companies. Crusoe borrows the money and builds the buildings. Oracle rents the buildings and buys the chips that go inside. And OpenAI, the maker of ChatGPT, rents those chips from Oracle. The plan, at this point, was for two buildings. June 2024, and the digging starts. A building full of machines this heavy needs strong footings. And normally, each one is a small building job in itself. A mold, steel bars tied together inside it, concrete poured in. Here, the steel arrived, already welded into cages, every cage the same size, and was lowered straight into the ground. The engineers had designed the footing so that no molds were needed at all, and a damaged cage could be swapped for an identical one on the spot. Then came the concrete, and a great deal of it. By September of the following year, the builder worked out a comparison for a local reporter. Enough for the foundation slabs of 6,100 houses. And the pouring was not finished. That first summer brought something nobody had ordered. On the 21st of August, 2024, with the job not yet three months old, Abilene recorded the hottest day in its history: 45 degrees Celsius. That day will come back when we get to the cooling. The steel came early. The first fabricated pieces were on the site within three months of the start. And by the fabricator's own count, the campus took some 25,000 tons of it, more than three times the iron in the Eiffel Tower. Because every column and beam belonged to the same grid, the frames went up one bay after another, each the twin of the last. Then the skin. The walls were not built on the site at all. They arrived as finished: insulated panels, hundreds to a building, and the crews hung 15 or 20 of them a day. A building the size of six soccer fields was closed against the weather in under eight weeks, so the work inside could begin while the outside was still new. Inside, the same idea ran all the way down. More than half of the electrical equipment was put together in a factory and delivered ready-made. Crusoe built switchgear in its own plants, so that it would not have to wait in a supplier's queue. Even the enclosures that fence in the hot air behind the computers were assembled on the floor and jacked up into place, which saved 20 days. The crews moved through the four halls in what the builder calls hopscotch. When the crew in the first hall finished, it jumped to the third, while the crew behind it moved from the second to the fourth. Each hall took about 10 months from its start to the day it was switched on. Not everything could be made in a factory. On the first two buildings, the builders report wind delays nearly every week and snow that lasted for days. At one point, the contractors faced a hold-up that could have cost 154 days, and together they cut it to 28. About six months in, with two buildings rising, the order changed. Not two buildings, eight at the same pace. The money grew with it to 15 billion dollars, most of it lent by banks led by J.P. Morgan. How much is that? More than $100,000 for every person who lives in Abilene. The city's part was a tax deal. For 10 years, it forgives 85% of its property tax on the buildings. And the site filled with people. In March 2025, about 1,500 were working there. By September, the builder was still taking on at least 200 new people every week. And on a typical day, by its own count, $10 million of work was installed. By December, there were more than 7,000 a day, around the clock. And the electrical contractor says its crews in West Texas came from 37 states. By the middle of 2026, by Oracle's count, about 20 million hours of work had gone into the place. One person working without ever stopping would need more than 2,000 years. A satellite passes over Abilene every few days, and its pictures show the whole thing happening. In June 2024, there is bare red earth where two buildings will stand. A year later, the first one has its roof and its rows of chillers. By September 2025, the first is running and the fourth has its roof. And that November, the frame of the eighth and last building was complete. So far, this is a very large shed. Three things turn a shed into a data center. Electricity has to come in. The computers have to turn it into work. And the heat has to get back out. Take them in that order. Electricity crosses the plane on a power line at hundreds of thousands of volts, because the higher the voltage, the less is lost along the way. No machine can use it like that. So the line runs into a substation, a yard of switches and giant transformers, that bring the voltage down in one big step. In the usual design, it is lowered again at the building to about 400 volts. Again, inside each cabinet of computers, to about 50. And once more, right beside the chip, where it arrives at less than one volt. The switches inside a chip are so small that they run on less than a volt. And that has a price. Power is voltage times current. So at less than a volt, a single AI chip needs more than a thousand amps. Five times what the main cable into a new American house is built to carry. Current like that cannot be sent far, which is why the last step down happens right beside the chip. What the chips do with that electricity is a film of its own, and we have made it. For this one, a single fact about them is enough. Nearly every watt that goes into a chip comes straight back out as heat. So a place that takes in the electricity of a city has to get rid of the heat of a city every second of the day. Inside the halls, liquid does the carrying. It takes most of the heat off the machines and hands it through a wall of thin metal to a second loop, the building's own water. That loop runs outdoors to the chillers that line every building, about 80 to a building and 640 in all. How much liquid? By the figures Nvidia gave when it launched this kind of rack, about two liters every second through a single cabinet. It goes in at 25 degrees Celsius and comes out 20 degrees warmer. Outdoors, what happens next depends on the weather, because heat only moves one way, from warm to cool. On a cool day, the air is colder than the water coming back from the halls, so a chiller of this kind can work like a car's radiator, with fans alone. As the day warms up, the air takes less, and compressors make up the difference, the way an air conditioner does. Now, think back to that August afternoon and 45 degrees Celsius. On a day like that, the air outside is as hot as the liquid leaving the chips. Nothing comes free, and the compressors do all of the work. A cooling plant has to be big enough for its worst afternoon, and Abilene's arrived in the first summer of the job. Either way, the heat ends up in the sky. Now imagine a data center with no air around it at all. Elon Musk says SpaceX will build them in orbit, out of its own satellites running on sunlight. Up there, every watt still comes back out as heat, and there is no air to carry it away. So how would you build one? That is our next film. Back on the ground, here is the water, a part people argue about. Many data centers cool by letting water evaporate, which takes less electricity and a great deal of water. This is dry country, and this loop is sealed. Filling it takes nearly 4 million liters of building from the city's supply. For all eight, that is what Abilene uses in about nine hours. After that, the companies say, it only needs topping up. In a whole year, less water than the city uses in half an hour. The city's water office expects an occasional full refill. Crusoe says it will never need one. No meter readings have been published. Nothing here is free, though. The price of cooling without evaporation is electricity, because fans and compressors do the work that the evaporating water would have done. This design spends power to save water. In April 2025, 10 months after the first digging, the core of the first haul was handed over. But nobody rolls cabinets worth millions into a haul on trust. First, the haul has to prove itself, and the usual way is in five rounds. Each machine is tested at its factory, again when it arrives, again before it is switched on, then on its own under load, and finally all of them together, with the power cut on purpose to see the backups take over. That last round has an obvious problem. The load is supposed to be the computers, and the computers are not here yet. So heaters stand in for them. Boxes that draw the electricity the computers will draw and give off the heat they will give off, while the engineers watch whether the power holds and the cooling keeps up. By the builders figures, a haul here is made for 25 megawatts. So a full test means the heat of 10,000 electric kettles, all boiling at once in a single room, and a cooling system that has to carry every bit of it away. So the first thing a brand new haul does is keep a room full of heaters cool. June 2025. One year in, and the machines arrived. They come as racks, already assembled. Steel cabinets a little over two meters tall that weigh about one and a third tons each. NVIDIA has said they are put together in Mexico by Foxconn, mainly for Stargate. NVIDIA, which designs them, counts 600,000 parts in one and 5,000 cables, about 3 kilometers of copper in a box the size of a wardrobe. Racks like these are too heavy for the raised floors of older data centers, so they stand on concrete. A rack is set in its place in the row and connected three ways: to power, to the cooling liquid, and to the network. Then it is one of hundreds in its hall and one of thousands on the campus. One rack draws as much power as about 30 Texas homes on a hot summer evening, and by the usual estimate costs about three million dollars. So the building, for all its concrete and steel, is the cheap part. One independent estimate puts the whole campus, machines included, at about 31 billion dollars, and most of that is the machines. Why nearly all of those chips come from one company is a film of its own, and we have made that one too. They kept coming. By December 2025, Oracle counted 96,000 chips delivered to Abilene. In three months of the following summer, it delivered 131,000 more, and by then, Oracle said, its customer was accepting each new batch within a day. The last connection is the one that turns thousands of machines into one. Fiber-optic cable links every rack, through switches, to all the others, so that a whole building of chips can work on a single job. It is also why the buildings stand so close together. The designers keep everything within about two kilometers, because, even for light, distance costs time. OpenAI says the fiber on this site would circle the earth 16 times. In July 2025, 13 months after the first digging, OpenAI said the first chips were at work, training and running its AI models. Two months later, on a Tuesday in September, when the thermometer reached 36 degrees celsius, the company showed the first building to the press. But that was one building, and seven more were on the way. Here, the story runs back into its power line. The old connection, the one left over from the Bitcoin plan, could feed about two buildings, not eight. How much electricity do eight need? About 900 megawatts, and there are two ways to picture that. By the Texas grid operator's own rule of thumb, it would run about 225,000 homes on a hot summer evening. Abilene has about 47,000. And on the July evening in 2026, when Texas set its record for electricity use, a campus like this at full power would have been about one percent of everything on the main Texas grid. Power on that scale cannot simply be ordered. So the builders went after it two ways at once. The quick way was to make it on the spot. In the lead builder's words, within weeks, they were designing and buying gas turbines. A power plant went up beside the buildings. Ten turbines, about 450 meters from one family's house. Half of them are descended from a jet engine, a kind that leaves its factory 95 percent assembled. The slow way was a second substation, able to carry five times the power of the first, on a yard of five hectares. Its first transformer was switched on nine months after work on it began. But the giant transformers it was designed around had not all arrived, so three of its five were temporary ones, put in to keep the job moving. With them, in March 2026, 21 months in, the whole yard was live. The yard was laid out with a spare transformer and a bypass, so that one transformer can be taken out, and another put in without switching the campus off. Its builder expected to have swapped all three stand-ins for the real machines by October 2026. Getting that much power is one problem. Drawing it steadily is another. When a model is being trained, tens of thousands of chips work in step. They compute together, then pause together for an instant to share their results, over and over. Each pause is a dip in power, and Oracle's own engineers write that at their scale, those swings can reach tens or even hundreds of megawatts, the electricity of a whole town, vanishing and coming back like a light switch. Transformers do not like that, and nor do turbines. Engineers from Microsoft, OpenAI, and NVIDIA have warned that at the wrong rhythm, swings like these could damage the grid's own machines. One of Oracle's answers is almost funny. In the gaps, a second program hands the chips a little throwaway arithmetic, just to keep them busy, so that the line stays flat. What about the gas plant now? Its filing with the state sets a ceiling, every turbine, every hour of the year. At that ceiling, they would put out the greenhouse gas of about 300,000 cars. Crusoe says the campus now runs on the grid, and the turbines are only for backup. How many hours they have really run has not been published. And backup, at this size, is a problem of its own. An ordinary data center keeps diesel engines outside, enough of them to carry the whole building if the grid fails. Abilene has diesel engines too. The state's file for the first two buildings lists 18, the biggest about as powerful as a freight locomotive. But add them all together, and they come to about a fifth of what those two buildings draw. They are there for emergencies. They could not carry the computers. So when Crusoe says the turbines are the backup, this is what it means. By its account, the power plant stands in for the rows of diesel engines a campus this size would otherwise need. It did not all go to plan. Early in 2026 came the first winter with machines running, and Bloomberg reported that winter weather hit some of the liquid cooling equipment and buildings were offline for days. The site, whose first summer had brought the hottest day in Abilene's history, lost buildings for days to the cold. The calendar slipped too. Crusoe had said all eight buildings would be finished by the middle of 2026. That June, Oracle told its investors that 42% of the capacity had been delivered. By September, it was six buildings of the eight, and as we made this film, the companies had not confirmed the last two. Go back to the ranch land where we began. 27 months after the first digging, there was a machine standing on it, and in September 2026, Oracle told its investors what that machine had done. OpenAI's GPT-6 Astra had been trained here. At the peak, more than 7,000 people a day were building this place. To run it, the plans call for a few dozen people in each building. The builders have not gone far. On the land next door, Crusoe is already putting up another campus, this one for Microsoft. So that is how one gets built. A power line that was already there. A building designed to be repeated. A year of concrete and steel. Machines to bring the electricity in and carry the heat out. And at the end, the chips, which by that estimate cost more than everything else put together. Whatever you make of these buildings, now you know what one is. This is Factory Up Close. One real factory, start to finish. Which one should we go inside after that? Tell us in the comments.